Capital Projects

The list below is a temporary list of capital projects that are in various stages of development or construction. 

 

  • Wastewater Treatment Facility Upgrade - Design Complete
  • Chestnut Street Trail Project - Nearly Complete
  • 2017 Streets and Alleys Rehabilitation Project - Notice to Proceed Issued
  • Guest House Roof Project - In Progress
  • Guest House and City Hall Painting Project - In Progress
  • Influent Flow Meter at Wastewater Treatment Facility - Contract Awarded
  • CV Starr Floor Drain Project - Construction in Progress
  • Coastal Trail Phase II - Bid Opened, Contract to be Awarded
  • Bainbridge Park Improvements - Out for Bid

 

 
    

 
   
   
   
   
   
 
 


   
 
  
  
Recently Completed
 
  

  • City Hall Gym Roof Replacement Project
  • Summers Lane Reservoir Project
  • Coastal Trail North and South
  • Green Alley Project Phase I & II

Contact Us

  1. Tom Varga
    Director of Public Works
    416 N. Franklin St.
    Fort Bragg, CA 95437
    Phone: 707-961-2824, ext. 117
    Fax: 707-961-2802
    tvarga@fortbragg.com

    Staff Directory
2011 Street Resurfacing Project Funding 
The City of Fort Bragg would like to thank the California Integrated Waste Management Board (CalRecycle) for the $70,399 grant that helped to fund the 2011 Street Resurfacing Project
CalRecycle